Piermont Public Library
Project Owner: Piermont Library District
Location: 153 Hudson Terrace, Piermont, NY
Architect: Colgan, Perry, Lawler Architect
Construction Manager: None
Contract Amount: $ 1,420,000
Square Footage: 4,750 SF
Start Date: Oct. 05
End Date: Oct. 06
-Newly constructed library containing reading
rooms, stack rooms, and site landscape.
State Street Firehouse
Project Owner: Village of Ossining
Location: 16 Croton Avenue, Ossining, NY
Architect: Pellaton & McCarthy
Construction Manager: None
Contract Amount: $ 2,089,000
Square Footage: 10,850 SF
Start Date: Sep. 03
End Date: Oct. 04
-New construction of firehouse including offices and kitchen within the interior. Truck bay addition outside of the firehouse